Sports Fields/Stadium and Pool Replacement Project at El Rancho High School

5,000 seats, a press box, synthetic track and field, a new practice field and new basketball courts. Additionally, both the baseball and softball fields will be completely new.

This project includes new team rooms, locker rooms, restrooms, concessions, ticket booths, coach's offices, storage spaces, a weight room, and a training room. Other scope includes scoreboards, sports lighting, outdoor sound systems, walkways, netting, fencing, and general site improvements.

Similarly, the designing of the pool facility project includes the construction of a new CIF pool and pool facility, bleachers, and a digital scoreboard/LED monitor.

Both projects will undergo parking lot re-configuration for optimized space and accessibility from both sides of the campus. The fence along the perimeter of the project will be upgraded for safety.

Sports Fields & Stadium Project: 

Architect: LPA, Inc.

Project Status: Construction Phase

DSA Approval: September 2023

Construction Start Date: Winter, 2023

Project Completion Date: Spring 2025

Estimated Project Budget: $47.4 Million

Bond Measure: 2010 Measure EE & 2016 Measure ER General Obligation Bonds

 

Pool Replacement Project:

Architect: LPA, Inc.

Project Status: Construction Phase

DSA Approval: September 2023

Construction Start Date: Winter, 2023

Project Completion Date: Spring, 2025

Estimated Project Budget: $22.2 Million

Bond Measure: 2010 Measure EE & 2016 Measure ER General Obligation Bonds

 
 Happening This Month:
 Pool Replacement Project
 Fabrication  Detailing June 2024
 Stadium
 Bleacher Footings June 2024
 Musco Lighting  Footings June 2024
 Masonry Walls for Building June 2024
 Scoreboards June 2024
 Sports Field
 Scoreboards June 2024
 
 
 
 
 
Elementary School Multi-Purpose Room Modernization Project
environments for students. These enhancements, meticulously planned from floor to ceiling, are designed to seamlessly blend with the existing campus settings without disrupting current programs or teaching methods. Notably, the MPR at Rivera Elementary School will receive a new stage platform, ensuring parity across all sites.
 
Upgrades will include the installation of ramp entry wheelchair lifts, acoustical paneling, new projectors and projector screens, and digital monitor installations. Moreover, the remodel will encompass a wide array of improvements, including interior finishes such as walls, ceilings, and new LVT floors. Suspended ceilings featuring skylights for natural lighting, a surround sound system, and upgraded LED and stage lighting will enhance the overall ambiance.
 
Additionally, the project will address ADA and fire safety standards, while also incorporating HVAC and roof access upgrades, window and door hardware updates, stage refinishing with new drapes, and the integration of a PA/clock/bell system. Lastly, new lunch tables and storage/shelving solutions will contribute to creating modern, functional spaces for students and staff alike.

 

Architect: Westberg+White Architects, Inc.

Project Status: Construction Document Phase

Construction Start Date: July, 2024

Project Completion Date: To be Determined

Estimated Project Budget: $16 Million

Project Milestones
 

Construction

Durfee

June 2024 - March 2025

South Ranchito

June 2024 - March 2025

Rivera

June 2024 - March 2025

Move-In

Durfee

March 2025

South Ranchito

March 2025

Rivera

March 2025